LATEST IMAGES AT HAPPY DUNG QUAT PROJECT – PHASE 4
Happy Dung Quat Interior Product Manufacture Factory Project - Phase 4 (Happy Furniture Phase 4) started in February 2022 and now has gradually come to the final stages of completion.
by Admin
TOPPING-OUT CEREMONY OF CHAN MAY QUARTZ MACHINING FACTORY
4.10.2022, DINCO E&C conducted the Topping-out Ceremony of Chan May Quartz Machining Factory project, located at Chan May - Lang Co Economic Zone, Phu Loc District, Thua Thien Hue Province.
by Admin
CONGRATULATIONS ON VIETNAM MIXING PLANT PROJECT ACHIEVING 300,000 HOURS OF SAFETY
On the morning of August 25, 2022, at Vietnam Mixing Plant, Binh Duong Province, DINCO Engineering and Construction Corporation held the event to congratulate the Vietnam Mixing Plant project on reaching 300,000 hours of Safety. Attending the event were Mr. Mai Xuan Phuc - Deputy General Director of DINCO, Project Management Board, Representatives of CAMSO Investor, Representativea of Royal HaskoningDHV Consultant and nearly 300 workers.
by Admin
IMAGES OF CONSTRUCTION PROGRESS OF CHAN MAY QUARTZ MACHINING FACTORY IN HUE AFTER 3 MONTH OF COMMENCEMENT
Images of Construction progress of Chan May Quartz Machining Factory in Hue after 3 month of commencement. Update on 18.08.2022
by Admin
HOW IS THE PROJECT OF “VN DANANG - RENTAL BUILDING HALL 3 ELECTRIC - DRAEXLMAIER AUTOMOTIVE – PHASE 2” CURRENTLY?
By the end of July 2022, the project has completed 53% of the work volume (while only 45% of the time has passed). The team has completed the renovation of the roof ventilator of the Hall 3 Factory, and the reinforcement of the existing roof of Hall 3.
by Admin
HAPPY DUNG QUAT PROJECT - PHASE 4 AHEAD THE CONSTRUCTION PROGRESS
Up to now, the project has been implemented for 4 months, the Site Management Board of Happy Dung Quat - Phase 4 project has completed 80% of the work. Dinco is rushing to implement the final works such as concrete pouring, workshop foundation, and steel work. With the current progress, Dinco is confident to finish the project 1 month earlier than contracted but still ensure the highest quality.
by Admin